System comissioning
After six and a half weeks on site, WRE has commissioned a new hydro scheme in South Somerset. Further information will follow when all landscaping and finishing works are completed.
After six and a half weeks on site, WRE has commissioned a new hydro scheme in South Somerset. Further information will follow when all landscaping and finishing works are completed.
Installation of the Ritz-Atro screw turbine in south Somerset has achieved a significant milestone with the installation of the mechanical equipment. With the help of a 200 tonne capacity crane (to overcome the long distance from crane access to site), the machine slotted in easily. The installation is on course to be ready for commissioning [...]